On 18 January 2023, Crnogorski elektroprenosni sistem energised the 110 kV line Lastva-Brezna, 100 kilometres long. Namely, in the previous period, CGES implemented numerous activities that were a prerequisite for commissioning the temporary connection 110 kV Lastva-Brezna in order to unload the transmission network from Nikšić (Perućica) to Podgorica to…